main navigation
my pace
Pleasantville Master Site Plan

Construction updates

Week of June 29, 2015

Alumni Hall

The brick and stone work remains on the back of the north wing. Contractors are working hard to complete this work next week.

The contractors are continuously working hard to complete the interior work in Alumni Hall.  The mechanical, electrical and plumbing work continues. Permanent power for Alumni Hall has been connected to the building and is operational. This is a major milestone for the building. The gas utility will follow. Painting and final room cleanings are underway on the upper floors. The carpet tile is also being installed. The architects have begun their punch list which is a great sign that the building is close to completion. The building is on scheduled to be turned over to Pace on July 29th.

The contractors have begun clearing their materials away from the courtyard area in front of Alumni Hall, in order to begin the necessary site work needed to create the first half of the new campus green.

Residence Hall B

Structural Steel framing on the south wing of the building is underway and is more than halfway complete. Please expect to see an increase of steel deliveries until this work is completed. The contractors will begin backfill operations in the north wing shortly. The modular units will begin arriving on campus in July once the work on Martin road is complete.

Site Work

The work on Martin Road continues this week. The installation of the utility work is slightly behind schedule due to weather and unforeseen site conditions. The road will remain closed throughout the day to vehicular traffic and reopen in the evening.  The road is now scheduled to be paved mid-July.  While this work is underway, Shirley Beth’s Way will be open to vehicular traffic to allow circulation to the north and west part of campus.

The utility work to cross the road off of Entrance 2 has been completed. The road will continue to be plated until the road is filled and paved. Please use caution while driving in this area and around campus.   

Athletics

Work on the fields continues. The final grade of Finnerty field and the final preparatory work for the installation of the synthetic turf will occur this week.   The turf installation for Finnerty field was delayed and is now expected to begin shortly. The prep work for the turf installation on the Multipurpose field will continue this week.  Work on the field house is progressing quickly. The rough mechanical, electrical and plumbing work will being on the second floor.  

All work is weather dependent; we will promptly notify the community of any changes.