main navigation
my pace
Pleasantville Master Site Plan

Construction updates

July 25, 2016

Site Work

Construction to restore Shirley Beth’s Way to its original appearance will begin on Monday. Site contractors will be placing stamped pavement along Shirley Beth’s Way beginning from the Miller Circle side of Shirley Beth’s Way and working its way up to the other side of Choate circle and down to the Goldstein Fitness Center/Alumni Hall intersection.  While this work is being conducted, these roadways will be closed to all pedestrian traffic.  Pedestrians are encouraged to use the pathway along the side of Miller and Lienhard.  Work on crosswalks throughout campus will continue. The crosswalks will be completed one half at a time to maintain one lane of traffic at all times.  

Prep work for paving at Martin Circle will continue this week.  Traffic will be maintained at all times.  Paving from Martin Circle down to the Service Road is tentatively scheduled to begin August 11th.   

There will be an early morning water shutdown on Wednesday July 27th to connect the sprinkler system at the softball field.  The shutdown will begin at 4:00 am and will be restored before 9:00 am.  The following buildings will be impacted during this time: Miller Hall, Lienhard Hall, Willcox Hall, Marks Hall, Costello House, Dyson Hall, and 901 Bedford.
 

All work is weather dependent; we will promptly notify the community of any changes.