Project Schedule

Week of April 26

1 Pace Plaza West – 4, 5 and 6th Floor Renovation

Construction continues on schedule:

4th Floor

  • Door Frame Delivery and installation will occur this week.
  • Acoustic spraying of the ceiling between 3:00 p.m.–10:00 p.m.

5th Floor

  • Floor layout and construction preparation will occur this week.
  • Partition framing and duct installation will commence at the end of the week.

6th Floor

  • Frame new roof openings will begin on Tuesday
  • Sprinkler and plumbing work underway
  • Acoustic spraying of the ceiling between 3:00 p.m.–10:00 p.m.

Roof Top Units Replacements

  • Abatement complete.
  • Demolition underway.
  • Steel dunnage reinforcement.

4th Floor

  • Sheetrock Installation