New York City Master Plan

New York City Master Plan

The New York City Master Plan is the physical embodiment of Pace’s mission. This mission combines the traditional hallmark of a Pace education, experience-based learning, with a rigorous liberal arts and professional curriculum. This powerful combination gives our graduates a deep understanding of their discipline, and real-world experiences that propel them to succeed in demanding and constantly evolving professions.

Pace University’s campus in Lower Manhattan is uniquely positioned to launch countless students towards the stars and beyond. New York is the greatest city in the world, and a revitalized and vibrant Lower Manhattan attracts driven young men and women looking to test themselves against the best that iconic financial institutions, major entertainment, communications and technology companies, bastions of artistic expression, and a major health care sector have to offer.

Key to this experience is providing students with the spaces on campus they need to learn, collaborate, and convene. By putting the student experience at the center of the New York City Master Plan, Pace is recognizing that learning takes place everywhere and the intentional and effective design of all spaces as opportunities for learning is critical to a successful Pace experience.


Construction Schedule

New entrance changes:

  • Beginning on Tuesday, October 16 at 7:30 a.m., the sidewalk leading to the B-Level elevators on the Frankfort side of the building will be closed as part of the construction for the NYC Master Plan. A new pathway will be up at 9 Spruce Street. The West Elevators will be re-opened on the B-Level. Further details and wayfinding information coming soon

 

Week of October 22, 2018
  • MEP work at 1 Pace Plaza and 41 Park Row
    • Electrical trace out, conduit installation, lighting, fire alarm installation
    • Install duct work
    • Sprinkler pipe installation
    • Plumbing Rough ins, trench drain installation
    • Installation of mechanical piping and new units
    • Control wiring
    • Installation of data wiring
    • A/V wire pulls
  • Interior Work at 1 Pace Plaza and 41 Park Row
    • Framing and sheet rock
    • Painting prep for ceiling archway
    • Bow tie ceiling painting (only at 1 Pace Plaza)
    • Curtain wall installation
    • Interior store front installation
    • Rail support installation
    • Installation of block walls and door bucks (only at 41 Park Row)
    • Terrazzo installation and floor finish (only at 1 Pace Plaza)
    • Installation of carpet (only at 1 Pace Plaza)
    • Duct opening framing (only at 41 Park Row)
  • Exterior work at 1 Pace Plaza and 41 Park Row
    • Foundation, slab prep, form work, and curbs
    • Concrete prep and pour at West Plaza (only at 1 Pace Plaza)
    • Rework of fence panels, Removal of scaffolding brackets and platform
    • Cleaning of exterior stone (only at 41 Park Row)
    • Installation of window surrounds 
    • Installation of stone panel (only at 41 Park Row)

All work will be completed between 6:30 a.m. -4:30 p.m.